Your Question:What is the size of the production hall of the same video that you sent yourself? It has several production lines
Please provide the minimum size of the production hall and storage space for the storage of the produced products How much capital do I need and how many production lines are there?
And how much is my monthly profit from this investment How many workers are needed per shift?
How much does it cost to buy each production line?
How many tons of raw materials do I need per month?
Answer You:
What is the size of the production hall of the same video that you sent yourself? It has several production lines
One complete tissue production line including 1 set tissue folding machine,1 set tissue cutting machine,1 set tissue single packaging machine,1 set tissue bundler packing machine and conveyors (It depends on your factory layout then can check price,but only small money)
How many square meters factory land are needed?
We should follow customer’s factory layout to design the production line.It can cover more or less factory land.Acturally,if enough big factory land,the production can be arranged as well.Normally,you should have enough space for production line,raw material storage and finished products storage.We designed 3 types of layout to you,please check the sizes as below,
Layout 1:production line size L13.3m*W13.807m,raw material storage L7m*W13.807m,finished products L5m*W13.807m.
Layout 2:production line size L15.2m*W14.002m,raw material storage L7m*W14.002m,finished products L5m*W14.002m.
Layout 3:production line size L17.7m*W13.546m,raw material storage L8m*W13.546m,finished products L5m*W13.546m.
How much capacity per day?
For example,if the single tissue paper packaging machine speed is 150pcs/min,8 hours per day for working hours,the capacity is 150pcs*60 minutes*8 hours*80%(It is effective working time,because it should take some time to put the jumbo rolls and adjust the machines)=approximate 57600pcs per day(8 hours.It can have more time for working)
How many tons of raw materials do I need per day?
If the folding machine speed is 120m/min*1.5m width for jumbo roll*0.013kg/square meter for tissue paper*2 PLY*2 rolls for 1/2 folded*60 minutes * 1 day (8 hours)*80%(It is effective working time,because it should take some time to put the jumbo rolls and adjust the machines)=3.6 tons per day (8 hours.It can have more time for working)
How much is your monthly profit from this investment?
Please check your jumbo roll price,your tissue selling price,your staffs charges,your water and electricity charges,then you can check out your profit from this investment(Because different country,the price and charges are different)
Let me provide our each machine power to you for easily checking cost as below,
OPFD-1450 Onepaper fully automatic facial tissue folding machine total power 44.75KW
OPQ-358S Onepaper fully automatic tissue paper automatic machine total power 6.02KW
OPR-118S Onepaper fully automatic single tissue paper packing machine total power 22.5KW
OPZ-30 Onepaper fully automatic tissue bundler machine total power 18KW
How many workers are needed per shift?
If one onepaper complete fully automatic tissue line,there are only 4 staffs needed.It including 1 staff for operating and controlling the machines,1 staff for repairing the machines and 2 staffs for box packing.
How much does it cost to buy each production line?
Maybe you think that our price is very high,but higher than that of other suppliers',but considering the high quality, our price is very reasonable.Our onepaper tissue machine with toppest fully automatic and advanced technology.And the famous brand of onepaper is well known in global customers.Actually,we can offer you tissue machine in different levels of quality.The economy model of semi automatic tissue machine is about 30% less.
Dear my friend, I hope that my answer to solve your queries.If any other needed,please tell us with no hesitation,we will try our best to service for you.